City of Burnaby Calls for NEB Panel Suspension over Kinder Morgan Pipeline

The Trans Mountain pipeline expansion project has failed to gain social licence from the provincial government, or any Lower Mainland municipality or First Nation, and the National Energy Board (. . .

Sourced through Scoop.it from: www.burnabynow.com

See on Scoop.itGreen & Sustainable News

“[…] In a fiery double-barrel blast, Gregory McDade, legal counsel for the City of Burnaby, fired one barrel at Kinder Morgan Inc., the company behind the expansion project, and the other at the NEB panel itself.

Citing Prime Minister Justin Trudeau’s promise to overhaul the NEB, which he criticized for becoming politicized, McDade said, “Burnaby should not be the last victim of a flawed process.

“The City of Burnaby calls upon this panel to suspend these hearings,” McDade said. “We call upon this panel to reset the process in a way that keeps faith with the public trust that the prime minister of Canada has claimed he has.”

McDade quoted Trudeau, who said, “Governments grant permits, but only communities grant permission.”

“Let me be clear, this pipeline does not have community permission,” McDade said. “Not from the community of Burnaby, nor from any of the Lower Mainland municipalities, nor from the public or the Government of British Columbia.” […]

The Trans Mountain pipeline was originally built in the 1950s and fed a number of B.C. refineries that made gasoline, diesel and jet fuel for domestic use.

The Chevron plant in Burnaby, where the pipeline terminates, is the only refinery left in the Lower Mainland. As it stands, it has to compete with other companies for the oil that moves from the pipeline.

A twinning of the pipeline would triple its carrying capacity. But that’s by no means a guarantee that the Chevron refinery will necessarily have access to more oil. Of the 890,000 barrels per day an expanded pipeline would move, 707,500 barrels are spoken for by 13 shippers in offtake agreements, with the oil destined for refineries outside of Canada.

“This is not a pipeline, I say, to bring oil to the Lower Mainland to supply local industry, to bring us gasoline, as the pipeline was in the 1950s,” McDade said. “This is a pipeline solely for export. No benefits to B.C. at all, but all the burdens and all the risk are borne here.”

Of the 49 interveners making oral presentations at the Burnaby public hearings, 19 are B.C. First Nations, including three key Lower Mainland groups – the Squamish, Musqueam and Tsleil-Waututh – all of whom are opposed to the project.

The expanded pipeline would increase oil tanker traffic to 34 per month from the current five. Musqueam Councillor Morgan Guerin said on Jan. 19 that the wake caused by tankers means small fishing vessels would have to stop every time a tanker goes by.

The Musqueam would view that as a potential infringement of their aboriginal rights to fish – a right that was affirmed in the landmark Sparrow case. […]”

 

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s