As Ed Davey, U.K. Secretary of State for Energy & Climate Change, spoke to the Environment Council in Brussels, saying: “We call for urgent action on reaching an ambitious 2030 energy and climate change agreement, to spur on investment in green, reliable energy,” at home in Britain t
>”Biomass with CHP
In contrast with dedicated power only biomass plants, biomass-fired combined heat and power installations are continuing to attract investment in the UK, given that they still qualify for significant government support.
A number of these projects have made advances over the previous few months. For instance, RWE Innogy UK (formerly RWE npower renewables), is in the final stages of commissioning its Markinch Biomass CHP plant in Fife, Scotland. This 65 MW plant will supply up to 120 tonnes of industrial steam per hour to paper manufacturer Tullis Russell. RWE Innogy is investing some £200 million (US$300 million) in the development, which was built by Metso and Jacobs.
In October 2013 Estover Energy revealed that planning consent has been granted by Dover District Council for its proposal to develop a £65 million (US$100 million) biomass-fired CHP in the South East of England at Sandwich, in Kent. Generating 11-15 MWe and 8-12 MWth, the plant will use locally sourced low-grade wood as fuel.
Construction is forecast to begin in spring 2014 at the Discovery Park science and technology park.
And in the July, the Helius Energy-developed CoRDe biomass energy plant in Rothes, Speyside, Scotland began operations, using by-products from nearby malt whisky distilleries to produce renewable energy and an animal feed protein supplement, Pot Ale Syrup. Construction began in 2011 on the 8.32 MWe and 66.5 t/h pot ale evaporator plan. The total development and construction costs of the project were £60.5 million. …”<
See on www.renewableenergyworld.com
Through this plant Tullis Russell paper mill will be supplied with 120t of steam per hour. In order to facilitate the paper mill with a secure supply of steam, three gas fired boilers will be installed.
Out of the total electricity generated, approximately 17MW will be supplied to Tullis Russell and 25MW will be exported.
LikeLike
Reblogged this on Greatpoetrymhf's Weblog.
LikeLike
Pingback: UK Bioenergy: Dedicated Biomass Plants no Competition for CHP Plants | Greatpoetrymhf's Weblog
Very descriptive post, I liked that a lot. Will there be a
part 2?
LikeLike